Sector: Oil & Gas
Province: Eastern Province
Client: Saudi Aramco
Contract Value: 6 Billion SAR
Year Completed: 2025 (in-progress)
Scope: The OMP projects are upstream projects related to the construction of Oil and Gas well sites, flow lines, trunk lines, laterals, headers, manifolds, transfer lines and any other pipelines with all associated facilities, such as instrumentation, communication, SCADA, fencing, site preparation, CP and OHPL, and civil works.
Sector: Oil & Gas
Province: Eastern Province
Client: Saudi Aramco-Total JV (EPC: Technip)
Contract Value: 450 Million SAR
Year Completed: 2014
Scope: Construction of the Conversion Package of SATORP refinery (5 Units), including the execution of underground piping, cable trenches, structural steel erection, heavy equipment erection, static and rotating equipment, piping prefabrication and erection, coating and insulation, electrical and instrumentation, and testing and pre-commissioning.
Sector: Oil & Gas
Province: Eastern Province
Client: Saudi Aramco-Total JV (EPC: Samsung/ Chiyoda JV)
Contract Value: 720 Million SAR
Year Completed: 2013
Scope: Construction of the Coker Unit of SATORP refinery, including the execution of all civil works, underground piping, cable trenches, concrete works for substation buildings structural steel erection, heavy equipment erection, piping prefabrication/erection and electrical instrumentation, testing and pre-commissioning.
Sector: Oil & Gas
Province: Eastern Province
Client: Saudi Aramco (EPCL SNC-Lavalin)
Contract Value: 1 Billion SAR
Year Completed: 2009
Scope: General Construction and bulk procurement for Shaybah GOSP-4 Grass Root Facility, our scope included but was not limited to civil, steel structure, buildings, piping fabrication and erection, rotating and static equipment installation, electrical, instrumentation, telecommunication and testing and pre-commissioning, in addition to the construction of the temporary construction facilities for SNC Lavalin and Saudi Aramco.”
Sector: Industrial
Province: Najran
Client: Najran Cement Company
Contract Value: 1.7 Billion SAR
Year Completed: 2008
Scope: Engineering, procurement, construction and commissioning a Greenfield Cement Plant with the capacity of 9,000-tonnes/day of desulphurized cement. The scope of works included a residential township (school, hospital, shopping complex, sports and recreation centers). China National Building Material (CNBM) was our main subcontractor and was responsible for the supply, installation and commissioning of all plant machinery.